The U.S. Interstate Highway system is almost complete. Regional networks are mature, and the new right of way is geared for housing. Luckily, we still see new alignments and the percentage is increasing for repaving and full reconstruction. This increase has led us to become efficient with sometimes difficult road improvement jobs. Let me explain.

Types of Rehab

There are three basic types of road rehabilitation all requiring a different approach to the data. While I have defined the types for data purposes, there are projects that can be a combination requiring a change in the process.

Full Rehab

This is the easiest and currently the most popular type we perform. The road may move horizontally and/or vertically and none of the previous roadway elements are to remain. Paving, curbs, and driveways are all replaced. Ditches will usually be reworked, if there is an underground storm system, it may change as well.

With everything being new, it may not make sense to refer to this as rehab. The reason is at some point the work you are doing will need to connect to something that will not be moving. Driveways, buildings and off-right-of-way drainage are required to match-in with the least amount of disturbance possible.

Mill and Fill

Asphalt paving does not have a great life in many parts of the country. Freeze-thaw in the North, water and heat in the South, and brutal sun in the West define the finite life and eventual repair of the wear surface. When spot repair is no longer possible, the road surface will be milled, and a new full-depth mat will be laid on the freshly compacted base.

We will go into detail later, but the curbs are usually in good enough shape to keep. We are now required to respect the vertical and horizontal constraints of the existing road. In addition, there are required minimum and maximum coverage and lifts for the base and wear surface. This gets difficult to work with, as there are many constraints plus having little or no ability to try and fit everything in.

Widening

Right of way acquisition is usually done with the future in mind, especially with larger arterial roads. As traffic counts increase, lanes are added to accept the load. When confronted with a widening job, we are concerned with two major points. First, the condition of the edge we are joining to, and then the topography of the extension. I will detail these in a moment.

The Basics

When doing rehab work, we usually go the route of a road job. Alignments and templates are a good start to get things right and, most importantly, a way to easily adjust as things change. The single biggest issue with rehab projects is the dynamic nature of all the parts that need to come together. Here is an outline of what we like to see.

Horizontal Alignments

Ordinary COGO (Coordinate Geometry) will be provided when doing a new road. Sometimes in a rehab job, the plans call out for following the existing road center. Yes, this is a loaded statement from the designers. There may be a line on the plans that might be an old alignment, or something drawn for convenience. Alignments with good instructions are easy to get on your screen, but what about that mystery scratch in the near middle of the road? There are several alternatives.

If you can’t get a good centerline from the CAD, you need to decide on how to guide machines for the work. A best fit centerline takes the edges of pavement and averages the distance between them to give you something to steer to. Here is a set of shots that were taken along the existing edge of pavement along the slip formed curb/gutter.

There are many ways to get an alignment, in this case I am using Carlson’s Best-Fit Centerline. You can use points or lines. Here I drew lines through the points with arcs in order to give the program a smoother start to figuring out a centerline. The alignment is drawn through the upper line (shown above) and will offset to get it to the approximate center.

I often times will do this on the other side of the road as well. When this is necessary, you need to either make a new averaged centerline or create two different roads using one for each side. These cases are generally for older, small streets and roads where environmental conditions have caused heaving and erosion to move the curb. Logic says we will replace those sections so this is a rare exception, not the rule. Knowing that, you are now able to fix real issues.

The new centerline is shown here. It deviates from the edge by almost 3-feet in the worst spot. This is too much. Changing the parameters will tighten things up. This is shown in the video.

With a good alignment to steer to, we will now work on the vertical.

Vertical Alignments

With horizontal alignments we are trying to get a centerline close to actual. With a vertical alignment, the stakes are higher. When the vertical profile corresponds with the centerline, it must follow road speed rules regarding cross-slope and the finished job needs to look good.

The job depicted above has 3D shots along the edge of pavement, as well as, centerline shots that are turned off. With these 3-points acting as cross-sections, we can create a good existing road surface as cross-sections. Don’t be alarmed if a contoured surface looks bad, a cross-section look is the best way to generate a finished product.

I have used Carlson’s Road Rehabilitation Profile command with good results. You will need to get things in order, including some of the outlined steps I will reference. When the pieces are in place, you will have access to the options shown in the dialog box. Lots of power is provided to automate a sometimes-difficult task.

With the alignments done be assured you will be revisiting these to make things work better. We will generate cross-sections to verify the quality of the data.

The following is the Carlson section alignment dialog box. There are enough options to give you the results you are looking for. I am using these options for the job in this article.

With the section interval and special stations defined, I will now create sections of the existing road to give me an idea of what I’m looking at.

Gathering Existing Data

I need to mention a critical point. When we work with clients who build models, we insist the shots are taken with a total station. GPS accuracy is not reliable for the number of required shots and would take too long to get low residuals. A robot and one person can shoot quickly and with accuracy to make sure we are not wasting time. We accept GPS shots only to fully rebuild the job after receiving good data.

Section Review

The production of cross-sections will be the true test of what needs to be done next. I have spent a lot of hours getting things ready for production on rehab jobs. The constraints of the existing features that remain and the rules imposed by the parameters of the road design make the task difficult. It may be necessary to rebuild the job several times in order to make everything work.

Also be aware of the hierarchy of importance in case something must give. For example, we need to keep the curb but need to go less than the required 2% slope. That’s an easy one, but there may be situations where several rules need to be flexed for things to work.

Here is one such example. The road is straight and calls for a 1.5% cross-slope. The right side of the road is almost flat. We need to review up and down station to see how far this extends. The solution here was a 75-foot curb replacement due to heaving of the existing curb and gutter.

With requirements that are often out of the requested values, this type of work takes more time. Many rehab jobs just want to follow the existing road, mill the existing surface and come back with minimum cover. This type of job still needs data to work correctly.

Carlson has a tool I have used with great success. The Match Reference Section Slope command allows you to specify the desired slopes and the limits of deviation to it. Here we are trying to get a 2% cross-slope with a variance to try and make things fit better.

After filling out the dialog box, the command has listed the varying cross-slopes generated by the settings.

Adjusting the Parameters

There are two tools I use to verify a rehab design. The first is the actual material to be used. At some point there was a takeoff done, and I want to make sure we are in the ballpark.

This is just a portion of the report, but the totals are in line. To adjust things, go back to the Process Options dialogue box and check the Adjust Template Grade Table. The side not associated with the Profile Grade will adjust. This may push the slopes outside the design parameters and require a variance to get the volumes down.

I will then plot the sections to verify the profile is doing what I want it to. With a small road like this there is not a lot of room to move, but if the job is several miles long small tweaks can bring big savings.  This particular road is getting 8-inches of white paving. The red is the sub-base needed to bring this up to grade. Had this trend continued for several stations in both directions, I would revisit the vertical profile to try and pick up some material savings.

Summary

The task may sound daunting, but the job needs to be broken down into the individual parts that make up the job. I have tried what seemed to be quicker and easier methods, but changes are near impossible and always take longer.

Approach each part of the process as a separate task and the delineation makes things easier to imagine. With more of these jobs coming along every day, it pays to be proficient.

I have featured Carlson because I have experience using the commands for road rehab projects. Other software can accomplish the same tasks. The commands will be different, but the procedure remains the same.